Kettering Electrical Stabling

Project Details

Client: Network Rail
Principal Contractor: Amey
Value of contract: TBC

Description of Works:

The supply and installation of steel sheet piles (AZ18-700) to form 3 No permanent retaining walls as part of the works to construct new sidings at Kettering Station where the new electric trains will be stabled as part of the overall Luton to Corby Electrification project.

 

The sheet piles were installed using a telescopic leader with a variable moment vibratory hammer. The piles were pre-augered prior to installation using the telescopic leader rig.