Client: Network Rail
Principal Contractor: Carillion PLC
Value of contract: £200,000

Description of Works:

The supply and installation of 1500m2of steel sheet piles and associated works to form a tied wall with anchor piles and tie bars and a cantilever wall – both walls being temporary and extracted prior to contract completion.

Piles were installed (and extracted) using a telescopic leader rig (TLR) and variable moment vibratory hammer, the TLR also pre-augered prior to pile installation