Old Oak Common Paddington Approach
Project Details
Client: Network Rail
Principal Contractor: Carillion Rail
Value of contract: On-going
Description of Works:
Old Oak Common Paddington Approach- PHASE 1 (2014)
The installation of a 360m long permanent retaining wall (the West Retaining Wall) using AZ steel sheet piles, with the longest pile being 14m. Piles were installed with a telescopic leader rig, which pre-augured prior to pile installation and with a variable moment vibratory hammer.
Old Oak Common Paddington Approach- PHASE 2 (2015)
The installation of permanent sheet piling to form 3 No. Retaining walls (the East Retaining Wall) using AZ steel sheet piles. Piles were installed with a telescopic leader rig, which pre-augured prior to pile installation and with a variable moment vibratory hammer.