A406 Power Road Bridge

Project Details

Client: TFL (Transport for London)
Principal Contractor: Hochtief (UK) Construction
Value of contract: £650,000

Description of Works:

The supply and installation of permanent steel sheet piles to form 2 No. retaining walls as part of the new bridge abutment works.

The piles were installed using a Giken Eco 700s Silent Piler in Supercrush mode (to preauger the piles). Due to the length of auger required a second service crane had to be utilised to support the auger.

Prior to the Giken arriving on site, 2 No. sets of starter piles were installed to launch the Giken from, using a Movax rig to preauger and vibratory drive the piles.