Happy New Year!
It’s 2016 and J N Piling are ready to take on a VERY busy year! We have 2 major projects starting in January followed by many more exciting and interesting jobs. Watch this space to see what we get up to and for photos and updates! Here’s to a prosperous 2016!
M3 Smart Motorway Plastic Piling for Highway England/Balfour Beatty
We recently undertook some plastic piling for Highway England on behalf of Balfour Beatty. The job involved the supply and installation of permanent plastic piling in Multilock form in lengths varying from 1.5m to 2.0m. These piles are to form permanent retaining...
Embankment Stabilisation at Chadlington, Oxfordshire
J N piling have been installing AZ14 Sheet piles near Chadlington on behalf of Carillion Construction for Network Rail to form a permanent retaining wall for railway embankment stabilisation using a Movax to pre-auger and drive. Work has now been completed....
Sheet Piling works at RedLane, Dorking
Work is going well on a permanent sheet pile retaining wall for embankment stabilisation at Red Lane in Dorking. Work was completed early September with all piles installed as planned. Photo Gallery
A406 Power Road Bridge, Chiswick
Updated photos and conclusion of the piling works at the A406 Power Road Bridge project. Photo Gallery Click for larger images
J N PILING- A406 Photo Update and NEW CONTACT DETAILS
J N Piling have been working hard at the A406 and have just started on the second phase of the project, expecting to complete the job in early August. We have been using the Giken Eco 700s to install steel piles to create a retaining wall on behalf of Hochtief...